PPVARR 6.0.4E VARIANCE REPORT DETAIL Report date 12/18/01
Page
1 Electrical Contacts
Ltd using qty ordered Time of day.. 09:13
ITEM #
ARTS FINISHED
VERSION ITEM
DESCRIPTION QUANTITY ORDERED 100.0000
PROD-ORD #
000017-0000 CUSTOMER # CUST P/O CUST ORD # QUANTITY PRODUCED 100.0000
PROD YIELD
100 BATCH QUANTITY 100
TIME FRAME 000 ENTERED DESC WAREHOUSE 01
PROD ORD DATE 12/13/01 SHOP DATE DUE 12/13/01 LAST TRANSACTION
DATE 12/13/01 HIGH PHASE 99
********* Q U A N T I T I E S **********
************ A M O U N T S *************
ESTIMATED ACTUAL VARIANCE ESTIMATED ACTUAL VARIANCE
PHASE MATL CODE DESCRIPTION
TOTAL QTY TOTAL QTY PCT COST
COST PCT
01 ARTS PURCH 100.0000 100.0000 100.0000
200.0000 100.0000 100
DATE ENTERED QTY
UNIT COST EMP # COMMENT EXTENDED AMT
12/13/01 100.0000 1.0000 100.0000
total 100.0000 200.0000 100.0000 100
PHASE OPER CODE DESCRIPTION
TOTAL HOURS TOTAL HOURS PCT COST COST PCT
01 TRCHBR TORCH BRAZE 100.0000
100.0000
1070.0000 1113.0000 43.0000 4
DATE ENTERED QTY
UNIT COST EMP # COMMENT EXTENDED AMT
12/13/01 100.0000 11.1300
122
1113.0000
total .0000
**** TOTALS *** *************
Unit Costs ************* ********** Extended Costs **********
estimated actual variance
estimated actual variance pct
Raw Material
1.0000 2.0000 1.0000 Raw Material
100.0000 200.0000 100.0000 100
Labor
10.7000 11.1300 .4300 Labor
1070.0000 1113.0000 43.0000 4
Overhead .0000 Overhead .0000 .0000 100
Final 11.7000 13.1300 1.4300 Final 1170.0000 1313.0000 143.0000 12